In early 2002,
building corporation «UkrAsiaBuild» won a tender as a nominated
subcontractor and since then, has been taking part in construction
of 56 km of division of main gas pipeline «Ananiev-Izmail. II
division, I turn, 1220 mm» which is designed to increase of supply
of Russian gas to Balkan peninsula.
In August 2002, work was completed on «fire»
connections at 7 crossings to active gas pipeline
«Ananiev-Tiraspol-Izmail».
This unique risk bearing type of works was
completed within 5 days at the highest professional
level. |